Diwali 2026 and Griha Pravesh: Order-By Dates for Made-to-Order Furniture, and the Order to Do the Work In
DecoraHubDiwali 2026 falls on Sunday 8 November, with Dhanteras on Friday 6 November. Griha Pravesh and wedding dates cluster in the same weeks. Almost everything DecoraHub sells is made after you order it, so the date that matters is not Diwali. It is the last day you can place an order and still have the piece in the house in time.
Work backwards from 6 November
Most buyers want the room ready by Dhanteras, not by Diwali night. That is the real deadline. Manufacturing and delivery times vary by product and city, and festival weeks are the busiest of the year, so confirm your date with the team through the contact page or on WhatsApp at +91 62903 50924 before you pay. As a planning guide, order in these windows.
| What you are ordering | Order by | Why |
|---|---|---|
| Custom-size dining table, custom finish, or a non-standard piece | Early October | A custom size is built from scratch. See how made-to-order works. |
| Standard dining table, sofa, TV unit or partition, outside the metros | Mid October | Longer transit, and assembly at your home |
| Standard large furniture, metro cities | Third week of October | Mumbai, Delhi NCR, Bengaluru, Hyderabad, Kolkata, Chennai |
| Wallpaper | Mid October | Printed after ordering, then installed. Allow a few days for the wall to be prepared first. |
| Carpets, wall art, clocks, mirrors | Third week of October | Smaller items, but courier networks slow down in festival weeks |
If you are reading this in the last week of October, ask the team what is available for your city rather than assuming it is too late.
The order the work has to happen in
Rooms get finished in a fixed sequence. Getting it wrong means furniture arriving before the wall is ready, or a partition going up after the carpet is laid.
- Wall repairs and painting. Any damp has to be fixed and dry before paper goes up. See which walls are safe.
- Electrical points. Sockets for an LED wall piece, a lamp on the console, or a floor point behind a sofa have to be planned now, not after the furniture arrives.
- Wallpaper. After painting has cured, before furniture arrives.
- Partitions. Fixed to the floor or ceiling, so they go in before the room fills up. See fluted glass partitions.
- Carpets. Laid on a clear floor.
- Large furniture. Dining table, sofa, TV unit, console.
- Wall décor. Hung last, once the furniture is in place, because its size and height are set by what sits below it. See metal wall art sizing.
Measure before you order, not after
The two things that go wrong on delivery day are a sofa that will not pass the door and a table too large for the room.
- Sofas arrive pre-assembled. Measure the door opening, the lift and the staircase landings. The method is in Will the Sofa Fit?
- Dining tables need 3 ft of clearance on every side where a chair is pulled out. See 4, 6 or 8 seater and the dining chair size guide.
- Carpets are sized against the sofa, not the room. See the carpet size guide.
- TV units should be longer than the screen. See the TV unit size guide.
- Wallpaper is billed by the area you measure. See how much wallpaper you need.
Griha Pravesh and wedding homes
A house being furnished from empty has a longer list and a fixed date, which is the hardest combination. Two things help. First, split the order: place the long-lead items, meaning custom sizes and anything for the main living and dining rooms, several weeks before the rest. Second, decide the metal finish for the whole house at the start, so pieces ordered weeks apart still match. The finishes are compared in gold vs rose gold vs black PVD.
Placement conventions that many families follow for a new home are in dining table Vastu.
Room by room, if you are starting now
- Living room. A marble centre table from ₹27,999 changes the room more than anything else for the money. Designs are in teapoy designs with prices. Add a carpet from ₹7,999.
- Dining room. A full table takes the longest lead time. If the date is close, new dining chairs from ₹9,999 refresh an existing table.
- Foyer. A console table with a mirror is the first thing guests see. See the styling guide.
- Walls. The quickest change of all. Metal wall art from ₹2,999 and wall clocks from ₹1,999, with no installation needed beyond a drill.
- Pooja and prayer spaces. Islamic wall art from ₹1,999, with placement covered in the placement guide.
Common questions
When should I order furniture for Diwali 2026?
Diwali is 8 November and Dhanteras is 6 November. Custom pieces in early October, standard large furniture by the third week of October for metro cities. Confirm your date with the team before paying.
Can I get delivery before a specific date?
Ask before you order. Share your city and the date, and the team will tell you what is possible.
What if something arrives damaged close to the date?
Read the refund and cancellation policy and the shipping policy before ordering, so you know the process.
Do you take bulk or project orders for a new home or office?
Use the B2B enquiry form.
Start with the dining tables, centre tables and sofas collections. Buyer photos are on the reviews page.